Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for May 2022 May 2022 AMBER GREEN GREEN GREEN Within Tolerance
Report for April 2022 April 2022 GREEN GREEN GREEN GREEN Within Tolerance
Report for March 2022 March 2022 GREEN GREEN GREEN GREEN Within Tolerance
Report for January 2022 January 2022 GREEN GREEN GREEN GREEN Within Tolerance
Report for December 2021 December 2021 GREEN GREEN GREEN GREEN Within Tolerance
Report for November 2021 November 2021 GREEN GREEN GREEN GREEN Moderate
Report for October 2021 October 2021 AMBER GREEN GREEN AMBER No Change
Report for September 2021 September 2021 GREEN GREEN GREEN GREEN No Change
Report for August 2021 August 2021 GREEN GREEN GREEN GREEN Moderate
Report for July 2021 July 2021 AMBER GREEN GREEN AMBER
Report for June 2021 June 2021 AMBER GREEN GREEN AMBER
Report for May 2021 May 2021 GREEN GREEN GREEN GREEN Significant
Report for April 2021 April 2021 AMBER GREEN GREEN AMBER No Change
Report for March 2021 March 2021 AMBER AMBER GREEN AMBER No Change
Report for February 2021 February 2021 GREEN GREEN AMBER AMBER No Change
Report for January 2021 January 2021 GREEN GREEN AMBER AMBER No Change
Report for December 2020 December 2020 AMBER AMBER RED RED Within Tolerance
Report for November 2020 November 2020 AMBER GREEN GREEN AMBER No Change
Report for October 2020 October 2020 AMBER GREEN AMBER AMBER Within Tolerance
Report for September 2020 September 2020 GREEN GREEN GREEN GREEN

Project Info

Project
Replacement for PathCAL/EROS and Labyrinth
Code
MVM141
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
David Kluth
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Oct-2020
Planning Date
29-Jan-2021
Delivery Date
31-Jan-2022
Close Date
14-Jun-2022
Overall Priority
Normal
Category
Discretionary