Report for November 2021

Report Date
November 2021

Achievements in this period

  • Phase 2 build completed.
  • UAT scripts written and testers recruited.

 

Issues

  • The project manager/business analyst is leaving the University at the end of the year and a new project manager has not yet been assigned. There is a risk that the project could be delayed if a new PM is not assigned soon.
  • Only seven users have volunteered to take part in UAT and there is a possibility that some will not find time to complete the tests. This means there is a risk that issues will not be identified during UAT. 

 

Next steps

  • Carry out UAT.
  • Address any issues identified through UAT.

 

Milestones

Build Build - Phase 2 03-Dec-2021
Accept UAT - Phase 2 17-Dec-2021
Deliver Project Delivery - Phase 2 31-Jan-2022
Build Completion of Flash conversions 31-Mar-2022
Close Project Closure 30-Apr-2022
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project status is green following milestone and budget change.
Change Status
Time
Significant
Cost
Moderate
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
88.0 days
Activity this month
11.1 days
Activity this year
25.0 days
Activity to date
78.7 days
Estimate to complete current year
9.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Replacement for PathCAL/EROS and Labyrinth
Code
MVM141
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
David Kluth
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Oct-2020
Planning Date
29-Jan-2021
Delivery Date
31-Jan-2022
Close Date
14-Jun-2022
Overall Priority
Normal
Category
Discretionary

Documentation