Report for November 2021
- Report Date
- November 2021
Achievements in this period
- Phase 2 build completed.
- UAT scripts written and testers recruited.
Issues
- The project manager/business analyst is leaving the University at the end of the year and a new project manager has not yet been assigned. There is a risk that the project could be delayed if a new PM is not assigned soon.
- Only seven users have volunteered to take part in UAT and there is a possibility that some will not find time to complete the tests. This means there is a risk that issues will not be identified during UAT.
Next steps
- Carry out UAT.
- Address any issues identified through UAT.
Milestones
Build | Build - Phase 2 | 03-Dec-2021 |
Accept | UAT - Phase 2 | 17-Dec-2021 |
Deliver | Project Delivery - Phase 2 | 31-Jan-2022 |
Build | Completion of Flash conversions | 31-Mar-2022 |
Close | Project Closure | 30-Apr-2022 |
- Approved budget
- 88.0 days
- Activity this month
- 11.1 days
- Activity this year
- 25.0 days
- Activity to date
- 78.7 days
- Estimate to complete current year
- 9.0 days
- Estimate to complete future years
- 0.0 days