Report for March 2022

Report Date
March 2022

Achievements this period

  • Known Bugs - work continues on the one remaining known bug.
  • User Guidance - work continues on creating and releasing User Guidance. 
  • Decommission feedback summary - only 3 response to date from the various previous decommission comms, who will be treated as exceptions.   
  • Decision - there will be a soft decommission date of 24th June from a user understanding perspective.  

Issues

  • none 

Next Steps

  • Fix remaining bug - CAL score summary placement.
  • Finalise  User guidance. 
  • Plan for Project Closure on 30th April 22.
  • The remaining Flash content conversion work and final old system decommission work will continue as part of BAU. 

Milestones

Milestone Due Date
Completion of Flash conversions 31-Mar-2022
Project Closure 30-Apr-2022
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Slight delay in delivery and increase in budget within tolerance. Overall cahnge within tolerance.
Activity
Approved budget
88.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Replacement for PathCAL/EROS and Labyrinth
Code
MVM141
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
David Kluth
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Oct-2020
Planning Date
29-Jan-2021
Delivery Date
31-Jan-2022
Close Date
14-Jun-2022
Overall Priority
Normal
Category
Discretionary