Report for May 2022

Report Date
May 2022

Achievements this period

  •  PGLTC and CULT approval for the new governance   process to ensure CAL content is maintained and up to date.
  • Access restricted for students to EROS/PathCAL & Labyrinth  
  • Further  discussion with Ophthalmology about their future system plans , demo of the benefits of Pathway undertaken. 
  • Closure report issued for approval

Issues

  • No new issues 

Next Steps

  • Closure report - ensure all approvers review and approve
  • Formalise and seek approval for the delay in project closure date , was 30th April. 

Milestones

Milestone Due Date
Project Closure 30-Apr-2022
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
At amber as there is has been a delay in the issue of and approval of the project Closure report
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Slight delay in delivery and increase in budget within tolerance. Overall cahnge within tolerance.
Activity
Approved budget
88.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Replacement for PathCAL/EROS and Labyrinth
Code
MVM141
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Gail Redford
Project Sponsor
David Kluth
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Oct-2020
Planning Date
29-Jan-2021
Delivery Date
31-Jan-2022
Close Date
14-Jun-2022
Overall Priority
Normal
Category
Discretionary

Documentation