Closure Report
Project Summary
Each year the College replace a number of PCs within its student computer labs, teaching spaces and meeting rooms (known as facilities managed machines). The replacements are based on a 5 year lifecycle. Some of the computers in this year's list were originally added to coincide with AV upgrades (Vets 1.4x rooms) however due to delays in delivery dates, it wasn't possible to install the new PCs before the students returned, so these computers were repurposed elsewhere and the 1.4x rooms will receive their replacement PCs when they were originally planned. The number of computers installed in the anatomy museum was reduced due to financial constraints and the perception from the local area that not all 7 computers were actually required. The future usage will be monitored and if an adjustment in numbers is required, this will be incorporated into another year's replacement cycle.
Outcome
Computer Labs
Anatomy Museum - 5 computers - completed
Vet School Cafe - 5 computers - completed
Teaching/Meeting Rooms
Greenfield Suite Main Lab - 1 computer - completed
IGMM East Nucleas Study Pod - 1 computer - completed
IGMM East L2 Study Pod - 1 computer - completed
IGMM East L3 Study Pod - 1 computer - completed
IGMM South S1.14 Seminar Room - 1 computer - completed
IGMM South SG.03 Meeting Room - 1 computer - completed
IGMM South S1.16 Meeting Room - 1 computer - completed
IGMM Centre C3.02 Meeting Room - 1 computer - completed
WTCRF Dining Room - 1 computer - completed
WTCRF (other) - 1 computer - completed
Vet 1.4x Rooms - 5 computers - computers repurposed in Chancellor's Building (computers that should have been replaced in 2019/20)
Vet 1.21 - 2 computers - completed
Vet F Block Clinical Skills - 1 computer (new addition due to AV upgrade) - completed
Greenfield Suite Side Rooms 4 and 5 - 2 computers - completed
Henry Littlejohn Suite - 4 computers - completed