Report for Oct 2022

Report Date
October 2022

Achievements

  • Mayank added the redirect from the old applications to the new ones.

Issues

  • No issues

Next Steps

  • None. Project is now considered closed
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
RAG Commentary
Project is now closed
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
No change
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BMS HHW & HHW2 upgrades
Code
MVM152
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Philip Larkman
Current Stage
Close
Status
Closed
Start Date
01-Sep-2022
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Oct-2022
Overall Priority
Normal