January 2023
- Report Date
- January 2023
Achievements this period
- List of computers has been added to the project brief and will be sent around the campus teams in early February.
- Original forecast number has currently been reduced due to room usage changes and reuse of computers taken out of other spaces. This will be checked in February, before purchase orders are raised, to ensure everything is correct.
Issues
- None
Next Steps
- Discuss replacements with local IT teams to ensure they are aware of the locations receiving upgrades.
- Purchase the replacement computers.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days