November 2023

Report Date
November 2023

Achievements this period

  • Lauriston Building has been cleared of any RAAC concerns, so we're now able to contact our data contractor to have the necessary network ports installed.
  • CAT6A cabling has been terminated in the Dermatology clinic room.

Issues

  • NHS funding for Lauriston learning hub is apparently still available, following all of the delays with the building warrant being approved and the previous concerns over RAAC.  We don't yet have a new timeframe from the NHS, so it is likely that this will be transferred into the 2023-24 upgrade project.

Next Steps

  • Request network cable/ports for Dermatology clinic direct from data contractor and then update the associated netjob.
  • Receive remaining supply only AV equipment.
  • Sign off desk swap for Mackenzie Medical Practice - January 2024.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrading of teaching spaces 2022/23
Code
MVM154
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Start Date
16-Sep-2022
Planning Date
n/a
Delivery Date
27-Jan-2024
Close Date
31-Jan-2024
Overall Priority
Normal

Documentation