December 2022

Report Date
December 2022

Achievements this period

  • Limited updates due to project manager's annual leave and Christmas closure.
  • Initial room list has been shared with the Vet School and Medical learning and teaching subgroup members, as well as with the development team in IS Learning Spaces Technology.

Issues

  • Vet School have decided not to take the AV equipment and furniture from the Chancellor's Elsie Inglis lab, so an alternative location will need to be found as soon as possible after the Christmas closure.

Next Steps

  • Prioritise list of rooms to upgrade this year based on available funding and update the project brief as necessary.
  • Organise visits to the rooms to discuss requirements with the associated teaching staff.
  • Create AV designs and then tender documents for each of the new room upgrades.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrading of teaching spaces 2022/23
Code
MVM154
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Execute
Status
In Progress
Start Date
16-Sep-2022
Planning Date
n/a
Delivery Date
28-Jul-2023
Close Date
29-Sep-2023
Overall Priority
Normal