Organisation
Work/Task Breakdown
Objective 1 - Requirements Gathering |
Who is Involved |
Outputs |
Review 'As-Is' Situation |
BA, BMTO |
As Is diagram produced during earlier piece of work |
Build user journeys to develop a 'To-Be' situation |
BA, BMTO, DLAM |
'To Be' diagram |
Produce prioritised Business Requirements Document |
BA, BMTO, DLAM |
Requirements Document |
Objective 2 - Development of New Portal |
Who is Involved |
Outputs |
Agree MVP |
DLAM, PM, BTMO |
N/A |
Produce Solution Design, Technical Documentation, User Guides |
DLAM |
Solution Design, Technical Document, User Guide |
Develop new BMS Honours Portal |
DLAM |
New BMS Honours Portal |
Objective 3 - Service Audits |
Who is Involved |
Outputs |
Accessibility Statement |
BMTO, DLAM, Accessibility Team |
Updated Accessibility Statement |
Data Protection Impact Assessment |
BMTO, DLAM |
New DPIA |
Equality Impact Assessment |
BMTO, DLAM |
New EQIA |
Objective 4 - Acceptance, Training and Go Live |
Who is Involved |
Outputs |
UAT new BMS Honours Portal |
DLAM, BTMO |
UAT Completed |
Deliver training on new portal |
DLAM, BTMO |
Training Delivered |
Launch new BMS Honours Portal |
BTMO |
Portal Live |
Project Estimations
Estimations for the Development phase will be completed at the point of the MVP being agreed. The estimate below covers time from Apps for Project Management and Business Analysis
https://secure.projects.ed.ac.uk/system/files/attachments/129340/mvm155_3_point_estimate.xls
Resources, Skills and Costs
Project Services
The budget of 50 days from IS Apps Project Services will cover
- Project Management
- Business Analysis
Learning, Teaching & Web - Digital Learning, Applications and Media (LTW DLAM)
- The LTW DLAM team will create a system design from the Business Requirements, and develop the new BMS Honours Portal
BioMedical Teaching Organisation (BTMO)
- As the main administrators of the BMS Honours Portal, the Student and Academic Services Team will be involved throughout the requirements, testing and implementation phases of the project
Project Governance
- Initially the project team will meet every 2 weeks, and also at key milestone sign off e.g. end of planning, BRD and Design completion
- Team meetings during the development phase will be decided ahead of the phase starting
Project Stakeholders
Business Area |
Role |
|
|
Project Services |
Project Manager - PROJECT TEAM |
||
Learning and Teaching |
Learning and Teaching Programme Owner |
||
ISG - LTW |
DLAM Development Team Manager - PROJECT TEAM |
||
ISG - LTW |
Head of DLAM |
||
CMVM |
Subject Matter Expert (Portal) - PROJECT TEAM |
||
CMVM |
Subject Matter Expert (Algorithm) |
||
Dean of BMS |
Budget Holder |
||
IS Applications - Project Services |
Portfolio Manager |
||
CMVM |
Project Sponsor |
||
CMVM |
Programme Owner |
||
CMVM |
Head of IT & Budget Holder |
||
IS Applications - Project Services |
Programme Manager |
||
CMVM |
Business Lead - PROJECT TEAM |
Project Estimations
MVP will be agreed during the project which will give an estimation for the development and UAT phase of the project.