Report for February 2023

Report Date
February 2023

 

Achievements in last period

  • Project Brief signed off by Sponsor

  • Project through planning with Apps Review

  • Regular sessions held with DLAM Development Team and BTMO to progress requirements

  • DLAM Development Team started first development sprint on 27th Feb

Issues ​

  • N/A

Next Steps ​

  • Complete Requirements sessions with BTMO and prioritise

  • Estimations for next development sprints

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
52.0 days
Activity this month
2.5 days
Activity this year
9.3 days
Activity to date
9.3 days
Estimate to complete current year
34.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BMS Honours Portal
Code
MVM155
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Chantal Reilly
Project Sponsor
Philip Larkman
Current Stage
Execute
Status
In Progress
Start Date
01-Nov-2022
Planning Date
01-Mar-2023
Delivery Date
31-May-2023
Close Date
28-Jul-2023
Programme Priority
1
Overall Priority
Normal