Report for February 2023
- Report Date
- February 2023
Achievements in last period
-
Project Brief signed off by Sponsor
-
Project through planning with Apps Review
-
Regular sessions held with DLAM Development Team and BTMO to progress requirements
-
DLAM Development Team started first development sprint on 27th Feb
Issues
-
N/A
Next Steps
-
Complete Requirements sessions with BTMO and prioritise
-
Estimations for next development sprints
- Approved budget
- 52.0 days
- Activity this month
- 2.5 days
- Activity this year
- 9.3 days
- Activity to date
- 9.3 days
- Estimate to complete current year
- 34.0 days
- Estimate to complete future years
- 0.0 days