An evaluation of the current EPPSAT and Simulated Patient databases is required, as these have been in use for around 10 years without any significant upgrades.  The systems are both built in MS Access, in some cases get used by the same staff, but were originally developed by different people.  Following the evaluation, a plan will be put in place to upgrade both systems.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2024 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
EPPSAT and Simulated Patient Databases
Code
MVM163
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Plan
Status
Suspended
Start Date
08-Jul-2024
Planning Date
n/a
Delivery Date
19-Dec-2025
Close Date
30-Jan-2026
Overall Priority
Normal

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.