August 2024

Report Date
August 2024

Achievements this period

  • No updates due to other priorities in getting ready for teaching.

Issues

  • None

Next Steps

  • Arrange meetings with EPPSAT and Simulated Patient co-ordinators to begin the analysis and requirements gathering processes.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EPPSAT and Simulated Patient Databases
Code
MVM163
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Plan
Status
In Progress
Start Date
08-Jul-2024
Planning Date
n/a
Delivery Date
19-Dec-2025
Close Date
30-Jan-2026
Overall Priority
Normal

Documentation