Overview
Background
Each year the College replaces the AV facilities in a number of teaching spaces across its estate. We are trying to move to a 5 year replacement cycle, however this is dependant on available funding. Unless told otherwise, the project will look to ensure all rooms added this year will be capable of running online teaching sessions. For financial year 2024/25 the replacements are below.
Scope (full list TBC)
Easter Bush:
- Vet School Room G.01
- Roslin Auditorium (part funded by School)
- EDSCCU Room 1.01 - some parts coming from Kennedy Tower closure
- TBC
BioQuarter:
- Installation of direct links between lecture theatres in Chancellor's Building (moved from 23/24 list into this one)
- Chancellor's Building seminar rooms - minor upgrades and ceiling mics
- Chancellor's Building seminar room 6 - change to clinical skills ward space (funded externally)
- Chancellor's Building Immersive Sim Room (funded externally)
- Chancellor's Building FU311 (funded externally)
- Chancellor's Building FU305 (funded externally)
- TBC
Central Area:
- Biomedical Sciences East/West Labs (funding only, work completed in 23/24 list)
- Anatomy Lecture Theatre (funded through Estates)
- Closure of Kennedy Tower teaching rooms - due to building being returned to NHS
- Dermatology Seminar Room
Wetern General:
- TBC
Objectives and Deliverables
To install the equipment purchased for last years teaching spaces priority list.
To replace the AV installations in the above rooms within a timely manor and with the least amount of inconvenience to the users.
Success Criteria
All rooms and equipment are upgraded and paid for within the financial year.