Project Status Reports

Title Report Date Time Cost Scope Overall Change
November 2024 November 2024 AMBER AMBER AMBER AMBER
October 2024 October 2024 GREEN RED AMBER AMBER
September 2024 September 2024 AMBER RED RED RED

Project Info

Project
Upgrading of Teaching Spaces 24/25
Code
MVM164
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Initiate
Status
In Progress
Start Date
09-Sep-2024
Planning Date
n/a
Delivery Date
31-Jul-2025
Close Date
n/a
Overall Priority
Normal