October 2024

Report Date
October 2024

Achievements this period

  • Met with members of the Vet School to discuss their concerns relating to the timing of annual upgrades.  Agreed that once the budget for this year is known and room priority list is created, additional staff will be included in the communications.  If it's possible, a preference would be to carry out some of the Vet School upgrades during the Easter break.
  • Initial room requests from Vet School have been added to the project brief.

Issues

  • The proposed budget for this year is 22% less than last year and none of the funding requested to be carried over, due to the staff resourcing issues from last year, has been approved.  This means that after the already committed spend for the delayed rooms from last year, the proposed budget for this year is 75% less than last year.  Other funding streams will be investigated to see what's possible.

Next Steps

  • Complete list of rooms requiring upgrades for the different campus locations and add to the project brief.
  • Prioritise list of rooms to upgrade this year based on available funding and communicate out to the relevant staff/groups.
  • Create AV designs and then tender documents for each of the new room upgrades.
Project Status
RAG Status
Time
GREEN
Cost
RED
Scope
AMBER
Overall
AMBER
RAG Commentary
Project moved to AMBER as we now have a proposed budget to work to. Whilst the budget is much lower than expected, once the committed spend from last years rooms is taken off, we will be looking at whether there are any additional funding streams available as well.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Upgrading of Teaching Spaces 24/25
Code
MVM164
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Initiate
Status
In Progress
Start Date
09-Sep-2024
Planning Date
n/a
Delivery Date
31-Jul-2025
Close Date
n/a
Overall Priority
Normal

Documentation