Report for May 2018

Report Date
May 2018

Achievements

Next Steps

  • None

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Walled Garden Pathfinder
Code
MVM312
Programme
MVM Research (MVMRES)
Management Office
ISG PMO
Project Manager
David Perry
Project Sponsor
Paul McGuire
Current Stage
Close
Status
Closed
Start Date
06-Jul-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2018
Programme Priority
3

Documentation