Completion Report

Project Summary:

Analysis of Resource Usage:

Staff Usage Estimate: 1 days

Staff Usage Actual: 1 days

Staff Usage Variance: 0%

Other Resource Estimate: 1 days

Other Resource Actual: 1 days

Other Resource Variance: 0%

Explanation for variance:

.

Key Learning Points:

.

Outstanding issues:

.

Project Info

Project
College Software as a Servive (SaaS) pathfinders [RStudio Server / OMERO]
Code
MVM313
Programme
MVM Research (MVMRES)
Management Office
ISG PMO
Project Manager
David Perry
Project Sponsor
Paul McGuire
Current Stage
Close
Status
Withdrawn
Start Date
07-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Aug-2017
Programme Priority
3

Documentation

Close