Impact

Priority and Funding

The whole project is Sponsor Funded. 

The project estimate and budget to deliver the project is 80 days for IS Applications and an additional 20 days for LTW. 

IS Apps and LTW resources will be charged separately to the Project Sponsor. However, the expectation is to include LTW work effort in project reporting to understand the financial status of the whole project. 

The original status of the project was a 'Normal' priority project. However, a project priority change to 'Higher' will be submitted through project governance on 16-08-2019. 

 

Impact and Dependencies

No dependencies to note. 

The preference is for MVM to collect a year's worth of data using the Fragile X Registry website, starting in October 2019. MVM's research project finishes in October 2020.

 

Project Risk

1 Unclear project scope GREEN GREEN Open Retain Sonya Campbell

view

2 IS Applications colleagues required to spend additional resource/effort in excess of budget GREEN GREEN Open Retain Sophie Milner

view

3 Project delivery falls behind schedule GREEN GREEN Open Reduce Sophie Milner

view

4 Dev Tech resourcing GREEN GREEN Open Reduce Paul Mcnulty

view

5 DevTech relationship with LTW GREEN GREEN Open Reduce Aileen Robertson

view

6 Extent of security required to deliver minimum viable product GREEN GREEN Open Reduce Bill Lee

view

7 Timelines to deliver wireframes and UI GREEN GREEN Open Reduce Aileen Robertson

view

8 Maria db may not be available for use GREEN GREEN Open Retain Alister Webb

view

 

Project Info

Project
Fragile X Registry website
Code
MVM316
Programme
MVM Research (MVMRES)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Sonya Campbell
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
05-Aug-2019
Planning Date
09-Aug-2019
Delivery Date
07-Feb-2020
Close Date
17-Apr-2020
Overall Priority
Higher
Category
Discretionary