IT Implementation of the NHS Lothian Health Board Framework Agreement - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2024 GREEN 40.0 days 28.4 days 9.9
Content
Status
In Progress
Current Stage
Execute
Start Date
Thursday, 6 June 2024
Planning Date
Tuesday, 9 July 2024
Delivery Date
Wednesday, 8 January 2025
Close Date
Friday, 31 January 2025
Project information
Project Code
MVM319
Programme
MVM Research (MVMRES)
Session
24/25
23/24
Organisational Unit
College of Medicine & Veterinary Medicine
Project Management Office (if relevant)
ISG PMO
Responsibility
User Services Directorate
Project Category
Compliance
Project Classification
Run
Project Type
Process Change
Project Size
Small
Project Complexity
Simple
Funding Source
College Ring Fence
Programme Priority
1
Overall Priority
Normal
Student Impact
Project deliverables will be used by staff on behalf of students