October RAG Status Report

Report Date
October 2024

Achievements this Period

  • We were able to meet the key Milestone of 31st October to complete the 1st Version of the SharePoint resource, even though we had constraints on Project Team time (see Risk 2 below).
  • All UAT sessions were scheduled and invitations sent out to SMEs.
    • Scenarios were developed and agreed by the project team by 1st November.
    • The User Scenario Testing will take place in November.

Issues

  • There were consistent resource constraints from the Key Stakeholders in the project team within MVM (Sponsor and Technical Lead time). More details can be found on the Risk Log: https://secure.projects.ed.ac.uk/unpublished/project/mvm319/risks/2

    • The risk has been lowered at the end of October when the Project Leads brought in additional support from a CMVM Computing Officer to work on fine tuning the Version 1 of the SharePoint resource. They were able to come into the project quickly, and had adapted the previously developed SharePoint site/Pages into a more user friendly version better geared towards our target audience. This will maintain the project siting at GREEN for this month, but both the PM and PrgM will continue to monitor the resource effort closely.
  • While not an issue, an item of note is the possible inclusion of a new Deliverable that is in Scope for the project, but was not accounted for in Planning nor was it identified for Budget and Timeline. The project Team is currently deciding if this new deliverable can be added to the work schedule and further updates will be provided in the November RAG report.

Next Steps

  • Conduct User Testing (Scenarios) with SMEs throughout November and capture comments and feedback to improve the resource in Version 2 edits
  • Complete Version 2 of the resource
  • Sign off on User Testing by the end of November

Milestones

Stage Milestone Due Date Previous Date Complete
Execute Phase 2 Complete - First SharePoint Version 31-Oct-2024 01-Oct-2024 Yes
Execute Phase 3 Complete - Second SharePoint Version 08-Nov-2024 22-Oct-2024 No
Execute Phase 4 Complete - User Testing 29-Nov-2024 01-Nov-2024 No
Accept Review Documentation 13-Dec-2024 No date available No
Deliver Delivery of Project Outcomes (Major Milestone) 08-Jan-2025 18-Nov-2024 No
Deliver Handover and Documentation Sign-Off 17-Jan-2025 25-Nov-2024 No
Close Project Closure Completed (Major Milestone) 31-Jan-2025 06-Dec-2024 No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
3.5 days
Activity this year
11.2 days
Activity to date
23.9 days
Estimate to complete current year
10.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IT Implementation of the NHS Lothian Health Board Framework Agreement
Code
MVM319
Programme
MVM Research (MVMRES)
Management Office
ISG PMO
Project Manager
Alexandra Mezeul
Project Sponsor
Mark Hay
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
06-Jun-2024
Planning Date
09-Jul-2024
Delivery Date
08-Jan-2025
Close Date
31-Jan-2025
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation