Impact

 

 

 

Priority and Funding

This project has been agreed as Priority 1 and is funded from MVM within the MVMBUS programme.

 

Impact and Dependencies

The timeline of this implementation project has been scheduled for delivery by the 3rd party supplier with expectation set March 2017 for launch (Phase 1) August 2017, whith Phase 2 completion by end of 2017. Should there be a delay to timeline then contingency dates will be agreed in discussion with the Project Board.

 

The Project Board agreed that development of the Single Sign On (SSO) proceed for Phase 1.

The Project Board wish to understand the feasibility and impact of incorporating the delivery of the integration with UoE's Identity Management service (IDM) into Phase 1. Until the prioritisation and scheduling of this joint work has been agreed with the 3rd party supplier it is not possible to provide a definitive date for this deliverable in the timeline and has been itemised seperately in the 3 point estimations. It is expected that a decision on the scheduling of this deliverable be approved at the May 2017 Project Board on the basis that it has been approved in principle for planning purposes.

 

 

Project Info

Project
Implementation of Vet Practice Management System
Code
MVM509
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Sue Murphy
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
19-Dec-2016
Planning Date
07-Apr-2017
Delivery Date
27-Sep-2019
Close Date
03-Jul-2020
Programme Priority
2
Overall Priority
Highest

Documentation