February 2017

Report Date
February 2017

Achievements in Last Period

  • FNS (Provet) on site 23/02/17.
  • Discussion with Provet on project governance, tools, meetings, comms etc. Tim King has agreed to deputise for David Argyle as Project Sponsor, and to chair Project Boards as required, with David remaining Executive Project Sponsor.
  • Discussion with business on authentication and identity management.
  • Provet have provided a demo platform populated with UoE data, Vet staff to be given access following signing of contract.
  • Provet have requested access to Tristan data to enable more efficient working with Vet staff on checking data and verifying iterations of the data migration; awaiting agreement on approach with IS campus IT support team.
  • Online meeting to be scheduled w/c 06/03/17 to go through planning with Provet, mainly focussed on functional (customisation) work.
  • Discussion with Development and Production teams on resourcing and priority of the non-functional work required; planning and estimation meetings pencilled in w/c 06/03/17 on assumption that MVM009 contract agreed and ready for signing.

 

Issues

  • No major issues; further delays to planning due to dependency on MVM009 contract agreement, although final version of contract ready w/c 27/02/17 passed for signing by David and Gavin.
  • We have requested Provet's top level plan for the sprints for the customisation work; this remains outstanding and until we have sight of this the milestones cannot be agreed.

 

Next Steps

  • Re-calibrate milestones following FNS visit 23/02/17 and online meeting 06/03/17.
  • Complete planning.
  • Review budget, resourcing, timeline and milestones.

The project current status is AMBER due to dependency on MVM009 contract.

 

Milestones

to be agreed during planning.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue: Current status is AMBER due to delay in planning (dependency on MVM009 contract which is expected to be resolved 06/03/17 and returning to GREEN).
Change Status
Activity
Approved budget
100.0 days
Activity this month
3.0 days
Activity this year
5.0 days
Activity to date
5.0 days
Estimate to complete current year
95.0 days
Estimate to complete future years
50.0 days

Project Info

Project
Implementation of Vet Practice Management System
Code
MVM509
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Sue Murphy
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
19-Dec-2016
Planning Date
07-Apr-2017
Delivery Date
27-Sep-2019
Close Date
03-Jul-2020
Programme Priority
2
Overall Priority
Highest