Report for January 2020
- Report Date
- January 2020
Achievements in Last Period
- Project closure report in draft pending signoff from Project Sponsor.
- Awaiting decision on budget for follow-on project which will determine whether outstanding non-critical tasks are carried over.
Issues
- No major issues.
- PM availability remains an issue due to commitments across projects.
- UoE user feed UAT incomplete so this work on hold pending a potential follow-on project; this work was not critical or contractual.
Next Steps
- Close implementation project.
Milestones
Project Closure | 21-Feb-2020 |
Project RAG is currently AMBER due to delays completing handover and closure (resource conflict: PM / Project Sponsor). Closure now expected by 21/02/20.
- Approved budget
- 395.0 days
- Activity this month
- 1.5 days
- Activity this year
- 23.3 days
- Activity to date
- 397.4 days
- Estimate to complete current year
- 4.5 days
- Estimate to complete future years
- 0.0 days