Report for January 2020

Report Date
January 2020

Achievements in Last Period

  • Project closure report in draft pending signoff from Project Sponsor.
  • Awaiting decision on budget for follow-on project which will determine whether outstanding non-critical tasks are carried over.

Issues

  • No major issues.
  • PM availability remains an issue due to commitments across projects.
  • UoE user feed UAT incomplete so this work on hold pending a potential follow-on project; this work was not critical or contractual. 

Next Steps

  • Close implementation project.

 

Milestones

Project Closure 21-Feb-2020

 

Project RAG is currently AMBER due to delays completing handover and closure (resource conflict: PM / Project Sponsor). Closure now expected by 21/02/20.

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project RAG is currently AMBER due to delays completing handover and closure (resource conflict: PM / Project Sponsor). Closure now expected by 21/02/20.
Change Status
Time
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
395.0 days
Activity this month
1.5 days
Activity this year
23.3 days
Activity to date
397.4 days
Estimate to complete current year
4.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Implementation of Vet Practice Management System
Code
MVM509
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Sue Murphy
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
19-Dec-2016
Planning Date
07-Apr-2017
Delivery Date
27-Sep-2019
Close Date
03-Jul-2020
Programme Priority
2
Overall Priority
Highest

Documentation