Project Brief

 

Project Name:

Psychiatry Standardisation

Date:

2/09/2016

Release: V0.2

Draft

Author:

 

Sarfraz Mohammed

Paul De'Ath

Owner:

 

Mark Hay

Client:

 

MVM

Document Number:

 MVM513

 

Revision History:-                            

Revision Date

Previous Revision Date

Summary of Changes

Changes Marked

06/01/17

 

Update project Brief

 

 

 

 

 

 

 

 

 

 

Document Sign-off

Name Role Date signed off
Mark Hay     Project Sponsor      19/01/2017
Paul De'Ath       IS Project Services Project Manager 26/01/2017
Paul Clark IS Head of MVM IT/Portfolio Manager 25/01/2017
Muriel Mewissen IS Project Services Portfolio Manager 23/01/2017

Sarfraz Mohammed

Jens Brinker

Project Support 18/01/2017

 

The project brief for MVM513 is the start of a coordinated series of projects to rectify long standing issues at Kennedy Tower where the majority of Psychiatry Staff work. For ease,  this project focuses on phase 1, which In principal is a time boxed series of activities, targeting Q1 2017 to complete:-

  • share existing firewall rules
  • confirm extent and support for up to 5 users to move from Kennedy Tower to 7 George Square - commenced
  • complete audit at Kennedy Tower - commenced (scope being developed)
  • ensure availability of new network switches for Kennedy Tower
  • plan and execute implementation of those switches
  • scope subsequent phases

Further projects will be initiated to address the Kennedy Tower network, George Sq access (virtualisation perhaps) and take into account the Psychiatry roadmap which may well extend into other locations

  • The architect also has a 3-5 year plan,  (this is Walled Garden) which should be documented to ensure all parties are in full agreement

Project Milestones (as of Monday January 09, 2017)

Target Datesort descending Previous Date Title Stage Complete  
27-Jan-2017 16-Dec-2016 Revise Project Brief Plan No

 

03-Feb-2017 No date available complete Kennedy Tower audit Plan No

 

24-Feb-2017 No date available Approve the Implementation plan for phase 1 Plan No

 

10-Mar-2017 No date available Scope out and present subsequent phases Deliver No

 

31-Mar-2017 No date available Implement Phase 1 Deliver No

 

05-May-2017 No date available Project Closure Close No

 

Risks  (as of Friday January 06, 2017)

Ref Title Impact Probability Risk Status Risk Owner Date of Last Review  
1 Key Stakeholder Engagement Medium Low GREEN Open Paul De'Ath 19-Dec-2016

 

Project Team will review the following and ensure they are captured for recommendations in future phases:-

  • Current systems can be broken down and reverse engineered to understand setup.
  • Training can be developed and delivered for users and IS support staff.
  • Research governance and training can be delivered and audited.

 

 

Project Info

Project
Remodelling of IS Support for Psychiatry Pilot
Code
MVM513
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Mark Hay
Current Stage
Close
Status
Closed
Start Date
20-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Jul-2017
Programme Priority
3

Documentation

Plan