Report for May 2017
- Report Date
- May 2017
Achievements
- The configuration change (access control lists) and new network switch changes were both implemented during the week commencing May 22nd, 2017 successfully
- The closure report and recommendation reports have been created and provisionally reviewed and approved by the project team
-
Issues
- No open risks- all can be viewed at:- https://www.projects.ed.ac.uk/unpublished/project/mvm513/risks
-
Next Steps
- The project team have agreed to review a change request before closing the project - details to be confirmed during the week June 05th, 2017
Milestones
-
25-May-2017 18-Jun-2017 Implement Phase 1 Deliver Yes 09-Jun-2017 12-May-2017 Scope out and present subsequent phases Deliver No 30-Jun-2017 05-May-2017 Project Closure Close No
- Approved budget
- 20.0 days
- Activity this month
- 5.3 days
- Activity this year
- 26.9 days
- Activity to date
- 26.9 days
- Estimate to complete current year
- 3.7 days
- Estimate to complete future years
- 0.0 days