Report for July 2020

Report Date
July 2020

Achievements

  • Fix student ranking and improved so can be listed in site
  • Removed dead code and deployed latest fixes

Issues

  • Developer availability still an issue meaning this project is slipping further behind schedule.

Next Steps

  • Add student ranking veto
  • Complete development for adding student projects that don't originate from the portal
  • Clean data for ranking algorithm
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Developer was reassigned to other DLAM work and was not able to make planned progress. This has caused further delay to delivery and has also impacted the 20/21 MVMLAT programme of work as this project should have been finished. Work is being prioritised to conclude and at programme level, looking at how to manage the impact to the 20/21 plan.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
Susan Patrick-Ridder, Programme Manager
Change Commentary
We did not complete as many tasks as expected in the month prior so the delay to the project's delivery is now a moderate change.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BMS - Honours Project Portal Future Support
Code
MVM516
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Michael Shipston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-May-2019
Planning Date
n/a
Delivery Date
12-Oct-2020
Close Date
12-Oct-2020