Report for August 2020

Report Date
August 2020

Achievements

  • Added off-portal projects for students
  • Fixed a bug in the suitability report download

Issues

  • Bug was discovered in the suitability report after it had been reviewed and deployed. Spent some time fixing this
  • Off-Portal projects took longer than estimated to develop because it affects so many different parts of the system

Next Steps

  • Deploy site
  • Close project
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Expect project to close first week in September
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Project taking longer to develop than estimated. Expected to deploy and close first week of September
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
BMS - Honours Project Portal Future Support
Code
MVM516
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Michael Shipston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-May-2019
Planning Date
n/a
Delivery Date
12-Oct-2020
Close Date
12-Oct-2020
Overall Priority
Normal
Category
Discretionary