- Report Date
- September 2020
Achievements
- Final delivery completed on Thursday 1st October
- there was a deployment on 28th Sept but this was rolled-back and fixes put in place:
- Add/Edit Supervisor did not render correctly
- A supervisor ranking a student for a project, would require that project to be reviewed for a department
- Preferred students not displayed on the report
- Deployment containedĀ minor changes, the bulk of the work having been completed:
- Add Last reviewed date to project suitability review list
- Recommended course label make consistent throughout site.
Issues
Next Steps
- Provide post-deployment project support if needed untilĀ 12th October
- Close project
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days