Name Project Role Date Signed Off
Mike Shipston Project Sponsor 08/11/2018
Paul De'Ath Project Manager (Project Team) 08/11/2018
Cristina Matthews

Business Lead/Senior User

08/11/2018
Muriel Mewissen Portfolio Owner 08/11/2018
Robert Beaton Service Management (Project Team) 06/11/2018

Note for WIS:-

As of November 7th, 2018 when this project is being submitted to WIS for QA at the end of planning, the Project only intends to progress Phase 1 which will require less than 10 days of the project effort. This relates to risk 3 becoming realised, though it's impact is currently reduced to impacting phases 2 and 3 - https://secure.projects.ed.ac.uk/unpublished/project/mvm526/risks/3

Post WIS on November 9, Claire Bradford and Alex Carter added as formal stakeholders. Claire is aware of the project and has the resource requirements. We have agreed Phase 1 delivery.

 

FYI:-

  • IS Production and App Dev  - No requirement for IS engagement outside of Service Management (SharePoint), all SharePoint deliveries will be supported by a combination of MVM and Unidesk into SharePoint team.

Project Info

Project
Zhejiang Institute Repository
Code
MVM526
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Paul De'Ath
Project Sponsor
Michael Shipston
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
28-Sep-2018
Planning Date
16-Nov-2018
Delivery Date
05-Jul-2019
Close Date
02-Aug-2019
Programme Priority
3
Overall Priority
Normal
Category
Discretionary