Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for May 2022 May 2022 BLUE BLUE BLUE BLUE
Report for January 2022 January 2022 AMBER GREEN GREEN GREEN
Report for November 2021 November 2021 GREEN GREEN GREEN GREEN
Report for October 2021 October 2021 AMBER AMBER AMBER AMBER
Report for September 2021 September 2021 AMBER AMBER AMBER AMBER
Report for July 2021 July 2021 AMBER AMBER AMBER AMBER
Report for June 2021 June 2021 AMBER AMBER AMBER

Project Info

Project
Cataloguing CMVM IS Services
Code
MVM530
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Myles Ewen
Project Sponsor
Sheila Fraser
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
17-May-2021
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2022
Overall Priority
Normal
Category
Discretionary

Documentation