Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for January 2023 January 2023 AMBER
Report for November 2022 November 2022 GREEN
Report for October 2022 October 2022 GREEN
September 2022 report September 2022 GREEN
Report August 2022 August 2022 GREEN

Project Info

Project
MVM Information Security Compliance
Code
MVM533
Programme
MVM Business Administration (MVMBUS)
Management Office
ISG PMO
Project Manager
Jonathan Henderson
Project Sponsor
Mark Hay
Current Stage
Initiate
Status
Suspended
Project Classification
Grow
Start Date
06-Jun-2022
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary