Report for February 2024
- Report Date
- February 2024
Achievements
- None.
Issues
- Issue: due to time pressures from within the academic team, the project has been delayed. Impact: The finalisation of the course content can be resumed by mid-March at the earliest which means a new launch date for the MOOC will need to be discussed. Next steps: A project meeting is set up mid-March to re-plan the project and to see what dates in regards to content writing and filming are feasible.
Next Steps
- Re-plan the project to set dates for the completion of course content and recording of the videos with the media production team.
- Plan marketing meeting and discuss and document marketing strategy.
- Get sign off on all course content.
- Continue to build out the course in FutureLearn.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days