Space Bridge Courses - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2025 BLUE 0.0 days 0.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 1 July 2024
Planning Date
Friday, 12 July 2024
Delivery Date
Thursday, 30 January 2025
Close Date
Monday, 31 March 2025
Project information
Project Code
OCP013
Programme
Online Course Production (including MOOCs)
Session
24/25
Organisational Unit
Learning Teaching and Web
Project Management Office (if relevant)
ISG PMO
Responsibility
Learning Teaching and Web
Project Category
Discretionary
Project Classification
Grow
Project Complexity
Standard
Alignment to Strategy 2030 and Adaptation & Renewal Team (ART)
Teaching and Learning
Overall Priority
Normal