Organisation

Work/Task Breakdown

This will be led predominantly from the consultation meetings where actions will be identified and outcomes delivered as required.  On this basis, tasks and resources will be outlined initially but will be subject to continuous review and updating.

Initial Tasks

Set up initial meeting with Payroll and Pensions to identify the best points of contact for the stakeholder group and estimate resource requirements 19 Dec. 14

Agree representatives on stakeholder group Dec. 14

Share project brief at P & P for agreement from HR Exec members Dec.14

Set up 4 x 2hr meetings for Stakeholder Group in Jan. 15 to develop processes and documentation - Include contingency planning for either statutory pay or enhanced and statutory length of service or removal of LoS criteria

Agree processes with stakeholder group by 2nd Feb. 15

Agree communications plan with stakeholder group by Feb. 15.

Collate data for people Committee Jan / Feb 15 

Implement communications / training plan from 2nd Feb. 15

Develop relevant employee/manager's guidance from 2nd Feb. 15

Next Phase

Await decision on length of service criteria and pay from relevant University Committees

Develop a Policy based on decisions from University Committees from Mar/Apr. 15

 

Resources Skills and Cost

Team

Resources - estimate days

Payroll

6 (1 rep)

Pensions

6 (1 rep)

Trade Unions

8.5 (3 reps)

Local HR Teams (MVM / HSS / SG / CSE)

25 (2 per team x 4 teams)

Local Admin Teams from business areas

21 (8 reps)

UHRS (HR Systems)

5

UHRS (Employee Relations)

10.5

Please see 3 point estimate for further detail

 

Project Info

Project
Shared Parental Leave
Code
P0173
Project Manager
Maureen Munro
Project Sponsor
Zoe Lewandowski
Current Stage
Plan
Status
Not Started
Start Date
09-Dec-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Category
Compliance

Documentation

Plan