Organisation

Work/Task Breakdown and Resource Estimates

TasksDeadlineLTW Effort
Management 8
Initiate  
Set up project framework02-Sep 
Agree project scope02-Sep 
Plan  
Create initial draft of project plan02-Sep 
Create Project Brief21-Sep 
Set up Project Governance21-Sep 
Planning Stage Sign Off16-Sep 
   
Execute11-Oct 
Project initiation06-Oct4
Proto typing (Course Design and Branding)  
Review of Dentistry to Learn mappings   
Training for porject team  
Use Case Review  
Start Migration Plan  
Content 2
Review of VLE Content  
Create content migration Plan  
Migration Plan 2
Complete Migration Plan  
Migration Plan Review and Sign-Off10-Oct 
  16
Deliver23-Dec 
Course Creation and content migration 30
Testing  3
Documentation (User guides) 3
Training and Launch 2
Total Estimated LTW effort 54

 

Resources Skills and Cost

The following skill sets will be required:

  • Learn site design, creation and configuration
  • Content migration
  • Training
  • Project management

Resources have already identified within LTW to meet these requirements and budget for the resources has been set aside as part of the wider Bespoke VLE Migration Programme

 

Project Governance

End stage sign-offs by Project Board

NameRole
Ann-Marie ScottProject Sponsor
Oonagh LawrieBusiness Sponsor
Annie HeaneyProject Manager

Project Info

Project
Dentistry VLE Migration Project
Code
P0261
Programme
ISG Virtual Learning Environment Projects (VLE)
Management Office
ISG PMO
Project Manager
Annie Heaney
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
01-Dec-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
23-Mar-2017

Documentation

Plan