February 2018

Report Date
February 2018

Achievements

  • First monthly session with EDE delivered
  • Learn wrap up meeting 8 Feb

 

Issues

 

Next steps

  • Lessons Learned report to be completed and approved by Project Board
  • Project to be closed following approval of Lessons Learned report

 

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Closure date extended to 17 November to allow time for lessons learned review but please note, delivery milestone completed on time Lessons learned report not yet completed. Additional planning work for ESSQ (MSc / Ophthalm / ChM) migrations has taken priority to ensure resources secured, timelines agreed and migration planned
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
The EEMeC Administration Migration Project
Code
P0267
Programme
ISG Virtual Learning Environment Projects (VLE)
Management Office
ISG PMO
Project Manager
Karen McPhail
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
01-Nov-2016
Planning Date
23-Feb-2017
Delivery Date
16-Jun-2017
Close Date
30-Apr-2018

Documentation