Organisation

Work/Task Breakdown

  • Project Brief and Plan
  • Research and document the existing MI.
  • Secondary research about what kind of management information other organisations collect.
  • Primary research - speaking to representatives for Project- Program- and Portfolio Managers, Apps SMT, and Business Administrators
  • Undertake analysis of these findings and compile them into an easily readable format (GAP Analysis)
  • Compile a research report outlining the current MI, the needs of the different stakeholders and suggestions for updating the MI.
  • Support production of the new MI.

NOTE-A survey will also be completed and information from this will be collated into a report. However, the survey is conducted separately from the project.

 

Resources, Skills and Cost

The project does not require any specialized skills. 

The project does not require any additional costs outside the project budget. 

 

Project Governance

Name Role
Jialei Ding Project Manager
Rhian Davies Project Sponsor

 

Project Stakeholders

Name Business Area Role
Jialei Ding USG Project Manager
Rhian Davies PMO Sponsor
Sheila Fraser USG Line Manager
Business Partners Various End users use MI to communicate with business partners
Portfolio Managers IS End user
Program Managers IS End user
Morna Findlay USG, Student Services End user

 

Project Estimations

Budget for this project is given at 8-10 Days. 

A breakdown of an estimation of the effort required by the different tasks:

Task Effort Notes on Duration
Create Project Brief 1 Day Depends on when it can be approved.
Create Project Plan 0.5 Days Small scale of project does not require detailed project plan. A High-Level project plan for quick reference will however be very useful.
Document Current MI 1 Days  
Primary Research - Interviews 2 Days Interviews will progress throughout June and July. Effort includes setting up meetings, preparing questions and travel. 
Secondary Research 0.5 Days  
Analysis of Research 1 Day Analysis of research will be agile as more information is added and will occur in tandem with the research. 
Compiling Report 4 Days Outline will be written up while the research is underway. The bulk of it (1 Day) will be done afterwards. Time will also be needed for reviews and approval.
Support for production of MI Dependent on the needs of the development team.  
Total (excluding support) 10 Days  

 

 

 

 

 

Project Info

Project
Management Information Review
Code
P0298
Programme
Project Management Office (PMO)
Project Manager
Jialei Ding
Project Sponsor
Rhian Davies
Current Stage
Initiate
Status
In Progress
Start Date
26-Jun-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Aug-2017
Overall Priority
Normal

Documentation

Plan