Organisation

Work/Task Breakdown

Task

Estimation

 

 

Create project brief

1.5 days

Gather information and understanding on how the current process works in each section of Applications Directorate

1 day

Understand what works well in the current process and what areas of it could be improved

0.5 days

Analyse the results of these interviews to understand what changes need to be made

0.5 days

Define the requirements for a new unified process

2 days

Document the new process

2 days

Communicate the new process through a role based communication plan

2 days

Link the new process up to project guidance and procedures for project managers 

0.5 days

Resources, Skills and Costs

  • Total time budget of 10 days
  • Verbal and written communication skills required for interviews and creating the new process. Good listening and emotional intelligence abilities required for interviews as well
  • Meeting rooms will be required for interviews 

Project Governance

  • Rhian Davies 
  • Bill Lee

Project Stakeholders

Project Stakeholders: PMO007: Unified Resourcing Process  
     
     
Name Business area Role
Alex Carter Service Management Stakeholder
Bill Lee Development Services Stakeholder
Dave Berry Enterprise Architecture Stakeholder
Mark Ritchie Project Services Stakeholder
Rhian Davies Project Services Project Sponsor
Ross Mennie Project Services Project Manager
Suran Perrera Production Management Stakeholder 

Project Estimations

Estimation Log | Project Management (ed.ac.uk) 

 

Project Info

Project
Unified Resourcing Process
Code
PMO007
Programme
Project Management Office (PMO)
Project Manager
Ross Mennie
Project Sponsor
Rhian Davies
Current Stage
Execute
Status
In Progress
Start Date
10-Jun-2022
Planning Date
n/a
Delivery Date
04-Aug-2022
Close Date
11-Aug-2022
Overall Priority
Normal

Documentation

Plan