Overview
Background
The various sections within Information Services have different processes for requesting and allocating resources to work on projects. This has created a complicated process where different sections within the Applications Directorate have to understand and remember the different ways of working, which is especially challenging for new staff. This has driven a desire for the Applications Directorate to adopt a unified resource requesting process that enables Project Services (and any other section) to request resources in a simple way which limits confusion.
Scope
- The scope of this project will be focused on the process dealing with requesting resources across the different sections of Applications Service
- The project will also create a basic FAQ system for the request resourcing process which will allow questions surrounding the new process to be answered.
Out of scope
- This project will only deal with the resource requesting process in the Applications Directorate and not other departments within the University
- The FAQ system will no be a final system but rather a basic system that will be continually updated as the new process is used
Objectives and Deliverables
Objectives and Deliverables |
Priority (MOSCOW) |
|
|
O1: To understand existing processes |
Must have |
D1: Create a AS-IS process summary |
Must have |
|
|
O2: To identify appropriate improvements to existing processes and documents required |
Must have |
D2.1: Create an AS-IS process summary |
Must have |
D2.2: Requirements document |
Must have |
|
|
O3: To document the new agreed process |
Must have |
D3.1: Create new guidance maps |
Must have |
D3.2: Create new process flows |
Must have |
|
|
O4: To communicate the new process |
Must have |
D4: Create a communication plan |
Must have |
Benefits
- A new process in place to request resources which is easier to follow and universal across all departments in the Applications Directorate
- Reduced time spent on resourcing by project managers and resource managers
- Easier to request resources using the new process which is the same of all sections
- Improved experience for staff being allocated to projects
- Improved experience for all staff who need to use the resourcing process
Success Criteria
- This project will allow all resourcing requests to be done through one process
- The process will be used across all of Applications Directorate for requesting resources
- The process will be delivered by mid-August 2022
- 80% of users will be satisfied with the new process
- The process will create new guidance and process maps which set out the new universal resourcing process
Project Milestones
Project Milestones: | PMO007: Unified Resourcing Process | ||||||||
Stage | Milestone | Original Date | Previous Date | Current Date | End of Stage | Complete | Date Completed | Notes | Actions |
Initiate | Start date | 10-Jun-2022 | 10-Jun-2022 | No | No | ||||
Plan | Planning date | 23-Jun-2022 | 23-Jun-2022 | No | No | ||||
Execute | Delivery date | 04-Aug-2022 | 04-Aug-2022 | No | No | ||||
Close | Close date | 11-Aug-2022 | 11-Aug-2022 | No | No |