Unified Resourcing Process - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2022 GREEN 8.0 days 11.0 days 7.0
Content
Status
In Progress
Current Stage
Execute
Start Date
Friday, 10 June 2022
Delivery Date
Thursday, 4 August 2022
Close Date
Thursday, 11 August 2022
Project information
Project Code
PMO007
Programme
Project Management Office (PMO)
Session
22/23
21/22
Organisational Unit
Project Services Directorate
Responsibility
Applications Development and Operations
Overall Priority
Normal