Achievements for this period
- Project brief created and approved on 22.6.22
- Reviewed and understood existing processes
- Carried out interviews with stakeholders to gather their opinions and feedback on the current resourcing process
- Started to identify appropriate improvements to the existing process
Issues
Next Steps
- Continue conducting interviews with other stakeholders
- Continue identifying appropriate improvements to the existing process
- Begin to document the new resourcing process
- Begin to communicate the new resourcing process
Milestones
Stage |
Milestone |
Original Date |
Previous Date |
Current Date |
End of Stage |
Complete |
Date Completed |
Execute |
Start date |
10-Jun-2022 |
|
10-Jun-2022 |
No |
Yes |
10-Jun-2022 |
Execute |
Planning date |
23-Jun-2022 |
|
23-Jun-2022 |
No |
Yes |
22-Jun-2022 |
Execute |
Delivery date |
04-Aug-2022 |
|
04-Aug-2022 |
No |
No |
|
Close |
Close date |
11-Aug-2022 |
|
11-Aug-2022 |
No |
No |
|
- Approved budget
- 10.0 days
- Activity this month
- 4.3 days
- Activity this year
- 4.3 days
- Activity to date
- 4.3 days
- Estimate to complete current year
- 5.7 days
- Estimate to complete future years
- 0.0 days