Report for June 2022
- Report Date
- June 2022
Achievements this period
- Project started
- Project Brief approved and noted in Apps Review 16/06/2022
- Completed Visio research and familiarisation
- Identified amendments and additions to preexisting framework with assistance of Key Stakeholder
Issues
- None
Next Steps
- Complete update of framework
- Devise communication plan
- User acceptance testing of framework
- Deliver framework by 29/07/2022
Milestones
Initiate |
08-Jun-2022 |
No date available |
Yes |
|
Plan |
24-Jun-2022 |
No date available |
Yes |
|
Execute |
19-Jul-2022 |
No date available |
No |
|
Deliver |
29-Jul-2022 |
No date available |
No |
|
Close |
03-Aug-2022 |
No date available |
No |
- Approved budget
- 10.0 days
- Activity this month
- 5.3 days
- Activity this year
- 5.3 days
- Activity to date
- 5.3 days
- Estimate to complete current year
- 4.7 days
- Estimate to complete future years
- 0.0 days