Impact

Priority and Funding

This project is of normal priority and has been funded for 10 days of effort for the Project Manager.

Impact and Dependencies

Dependencies:

  • No known dependencies 

Impact:

  • Induction link guide for new start process 
  • Central point of information where all staff can come to ask their first point of point of contact

Lessons learned from previous projects

Prior Interns have conduct projects, where they have addressed stakeholder availability as a risk. There will be regular communication among the Project Manager and Stakeholders to make sure that everything is done efficiently.

Project Risks

Ref     

Title                                                                                                      

Initial Risk      

Current Risk        

Status     

Management Approach

    Risk Owner

Date of Last Review

1

Project Completion during the designated timeframe

GREEN

GREEN

Open

Transfer

Rachel Miya Malouf

 

2

Staff availability to participate in Survey

AMBER

GREEN

Open

Reduce

Rachel Miya Malouf

 

3

Current information links not working

AMBER

GREEN

Open

Reduce

Rachel Miya Malouf

 

Project Info

Project
Information Signposting
Code
PMO010
Programme
Project Management Office (PMO)
Project Manager
Rachel Miya Malouf
Project Sponsor
Dawn Holmes
Current Stage
Close
Status
Closed
Start Date
10-Jun-2022
Planning Date
n/a
Delivery Date
28-Jul-2022
Close Date
03-Aug-2022
Overall Priority
Normal

Documentation

Plan