Report for June 2022
- Report Date
- June 2022
Achievements this period
- Project started
- Project Brief approved and noted in Apps Review 23/06/2022
- Created and sent out MS Form survey to gain information from project services staff on useful guidance
- Document for guidance created
Issues
- None
Next Steps
- Review survey responses
- Outline useful links onto the guidance document in alphabetical order
- Report old links (5+ years)
- Deliver framework by 29/07/2022
Milestones
Initiate |
10-Jun-2022 |
No date available |
Yes |
||
Plan |
22-Jun-2022 |
No date available |
Yes |
||
Analyse |
|
07-Jul-2022 |
No date available |
No |
|
Design |
15-Jul-2022 |
No date available |
No |
||
Deliver |
22-Jul-2022 |
No date available |
No |
||
Close |
29-Jul-2022 |
No date available |
No |
- Approved budget
- 10.0 days
- Activity this month
- 4.4 days
- Activity this year
- 4.4 days
- Activity to date
- 4.4 days
- Estimate to complete current year
- 5.6 days
- Estimate to complete future years
- 0.0 days