Report for June 2022

Report Date
June 2022

Achievements this period

  • Project started
  • Project Brief approved and noted in Apps Review 23/06/2022
  • Created and sent out MS Form survey to gain information from project services staff on useful guidance 
  • Document for guidance created 

Issues

  • None

Next Steps

  • Review survey responses 
  • Outline useful links onto the guidance document in alphabetical order 
  • Report old links (5+ years)
  • Deliver framework by 29/07/2022

Milestones

Stage         

Milestone                         

Due Date             

Previous Date           

Complete     

Initiate

Project Started

10-Jun-2022

No date available

Yes

Plan

Project Planning

22-Jun-2022

No date available

Yes

Analyse

Analyse

07-Jul-2022

No date available

No

Design

Document Creation

15-Jul-2022

No date available

No

Deliver

Product Delivery

22-Jul-2022

No date available

No

Close

Closure Report

29-Jul-2022

No date available

No 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
None
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
10.0 days
Activity this month
4.4 days
Activity this year
4.4 days
Activity to date
4.4 days
Estimate to complete current year
5.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Information Signposting
Code
PMO010
Programme
Project Management Office (PMO)
Project Manager
Rachel Miya Malouf
Project Sponsor
Dawn Holmes
Current Stage
Close
Status
Closed
Start Date
10-Jun-2022
Planning Date
n/a
Delivery Date
28-Jul-2022
Close Date
03-Aug-2022
Overall Priority
Normal

Documentation