Impact

Priority and Funding

  • This project has normal priority.
  • This project has been funded 10.0 days of effort by the Project Manager, funded by the PMO.

Impact and Dependencies

The project will make APM resources more visible to students. Additionally, this project will also outline a long term communication plan, detailing additional ways to raise student APM awareness, which is likely to have a long term impact on the usage of APM resources by student.

No known dependencies at this time. 

Lessons learned from previous projects

Previous intern projects have faced issues in regards to time to complete the project. As the internship is only 12 weeks, this restricts the amount of time spent on the project as well as shortening the milestone deadlines. In order to limit the impact of this, I will ensure I am making large amounts of progress each week in order to meet all milestones by the desired dates.

Additionally, previous intern projects have faced communication and progression issues in regards to contacting the project sponsor and finding time availability for regular meetings. In order to learn from this, I will ensure that progress is still being made by ensuring that in between meetings, there are large chunks of tasks to be done to ensure that progress is still occurring. Further, if I am lacking guidance or advice that isn't project specific and my project sponsor is unavailable, I will consult other senior staff in the PMO in order to ensure obstacles are overcame.

 

Project Risks

Ref  Title  Initial Risk  Current Risk  Status     Management       Approach  Risk Owner  Date of Last Review  
1  Lack of Project Sponsor Availability  GREEN  AMBER  Open      Retain  Dawn Holmes  28-Jun-2024

 view

2  Project Incomplete by end of Internship  GREEN  GREEN  Open      Avoid  Dawn Holmes  28-Jun-2024

 view

 

Project Info

Project
APM Awareness for Students
Code
PMO018
Project Manager
Amber De Sousa
Project Sponsor
Dawn Holmes
Current Stage
Close
Status
Closed
Start Date
12-Jun-2024
Planning Date
10-Jul-2024
Delivery Date
16-Aug-2024
Close Date
16-Aug-2024
Overall Priority
Normal

Documentation

Plan