Project Summary
The university has a corporate partnership with the Association for Project Management (APM), and can access a wide range of benefits and resources as a result. These resources are not available to students, they can instead become an individual member at no cost. Most students are unaware of this opportunity and therefore this project aims to create tools to raise awareness amongst students of what APM resources are available to them.
This project involved creating resources to aid student access to APM resources. This included creating a student guide detailing what APM is, How to make an APM Student account and what resources students have access to with their membership. It also resulted in the creation of an APM student accessibility guide, detailing the prior knowledge needed for each APM resource as well as how useful students might find them. This then went onto show students potential "Learning Paths" which were resources they may want to access and in which order, based on their wants and needs. These APM resources are to be used and distributed to students by the PMO in Project Management training or other Project Management activities following on from this project. There was also the creation of an APM long term student communication plan, where any potential out of scope APM ideas were recorded for future projects as well as different contacts that may be interested in APM. All of these together aim to make APM student membership promotion increase
Objectives and Deliverables Achieved
No. |
Description |
Priority (MOSCOW) |
Objective/Deliverable Met? (Yes / No) |
Comments |
O1 |
Create tools to make student APM resources more accessible |
Must Have |
YES |
NONE |
D1.1 |
Create Digital Student Area on SharePoint which contains all useful documents and links for students to use APM |
Must Have |
NO |
Student area draft (graphics displaying how this would look) has been created yet this is still to be actually created as it requires review by numerous PMO stakeholders first and due to annual leave this isn't possible before project closure. |
D1.2 |
Create APM Student Guide document detailing all resources available to students as well as how to use APM |
Must Have |
YES |
|
D1.3 |
Create APM Student Accessibility Guide breaking down what resources require no prior knowledge of PM |
Should Have |
YES |
|
O2 |
Create long term communication plan to promote potential further student APM awareness following project |
Must Have |
YES |
NONE |
D2.1 |
Create Longer term Student APM communication plan to promote further student awareness |
Must Have |
YES |
|
D2.2 |
Communicate plan to key PMO stakeholders to foster future APM awareness |
Must Have |
YES |
NONE |
O3 |
Identify all student versus staff APM resources |
Must Have |
YES |
NONE |
D3.1 |
Create Gap analysis displaying different APM resources and who has access to them to support staff understanding |
Must Have |
YES |
There was some initial difficulty with this as there was a lack of clarity in regards to accessing the corporate partnership and this resulted in a delay of delivery for this deliverable. Who can Access What- Gap Analysis Student vs Staff Resources.png |
Analysis of Resource Usage:
Staff Usage Estimate: 10 days
Staff Usage Actual: 10.4 days
Staff Usage Variance: 0.4 days (4%)
Other Resource Estimate: £0
Other Resource Actual: 1.14
Other Resource Variance: 0%
Resource Area/Team |
Original Estimate (days) |
Actual (days) |
Difference |
Project Manager |
10 |
10.4 |
0.4 |
Project Sponsor |
N/A |
N/A |
Explanation for Variance
Due to the detail given to the deliverables and the quantity of research required to create these, this meant that the Project required more effort than originally anticipated. Because of this, the project went over budget by 1 day (discussed and approved by Project Sponsor) in order to ensure the deliverables created were to a high quality.
Outcome
The outcome of this project is the resources created including the two student guides as well as the communication plan. These detail all student essential APM access information as well as helping students to make the best use of the resources they are given access to. This will likely make it easier for those providing Project management training to introduce students to APM without taking up too much time within their training slot. Equally, this will also let students understand all of the resources APM offers to them and why they should be interested in them which is likely to result in more effective student training sessions. On the other hand, with the long term communication plan, this can help with the generation of APM initiatives within the future as well as helping more staff promote APM to students. This is likely to promote APM to students longer term as this project itself is unable to do any direct student promotion activities or events.
Key Learning Points
The main learning points as a result of this project are:
- It is detrimental to have Sponsor engagement and sign off throughout the entire lifecycle of a project to ensure that each stage can be completed effectively.
- It is good practice to ensure that project deliverables are possible within the allotted effort of the project and to consider what deliverables are going to be during effort estimation.
- It is good practice to plan your deliverables in detail during the planning stage and when setting MOSCOW ratings as this can ensure that the ratings are correct and that your deliverables created are as effective as possible for the project aim.
View the learning points in more detail below:
1 |
19-Aug-2024 |
Was detrimental |
||||
2 |
19-Aug-2024 |
Should implement as good practice |
||||
3 |
19-Aug-2024 |
Should implement as good practice |
Outstanding Issues
Issue Number |
Description of Issue |
Owned by |
1 |
Resources are still to be reviewed and approved by PMO stakeholders due to lack of sponsor/executive sponsor availability due to annual leave. Therefore PMO stakeholders are to review these resources, and make any necessary changes. |
PMO (Dawn Holmes) |
2 |
Student Resource area of PMO is to be created following this project as resource approvals weren't able to be completed within the lifespan of this project due to annual leave. Therefore PMO are to create this page based on graphics produced following on from the project. |
PMO (Dawn Holmes) |