August 2024
- Report Date
- August 2024
Achievements this period
- Final Drafts of Project deliverables have been created for the Student Guide, Student Accessibility Guide as well as the Long term Communication Plan.
- Graphics displaying SharePoint created
- Documents passed onto PMO and contained within private PMO SharePoint (until they can be reviewed and published)
- Closure Report Created and approved by Sponsor.
- All relevant logs have been updated and any issues and risks have been closed.
Issues
- No issues identified this period.
Next Steps
- Closure report approval by Apps Review
- Documents reviewed by Executive Sponsor and then published.
Milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Initiate | Project Started | 11-Jun-2024 | No date available | Yes | |
Plan | End of Planning | 10-Jul-2024 | No date available | Yes | |
Analyse | Analysis Complete | 17-Jul-2024 | No date available | Yes | |
Build | Student Guides Created | 06-Aug-2024 | No date available | Yes | |
Build | APM Long Term Communication Plan Completed | 08-Aug-2024 | No date available | Yes | |
Deliver | Documents Distributed | 14-Aug-2024 | No date available | Withdrawn | |
Close | Project Complete | 16-Aug-2024 | No date available | Yes |
- Approved budget
- 10.0 days
- Activity this month
- 0.4 days
- Activity this year
- 10.4 days
- Activity to date
- 10.4 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days