Summary aim of project To implement Oracle DataGuard for the HR and Payroll system to bring it in line with other systems that have migrated.
Oracle DataGuard ensures high availability, data protection and disaster recovery for enterprise data.
Further Decision
After a review of the compliance projects submitted for 17/18 the difficult decision was made to withdraw this project and not implement dataguard for HR & Payroll eBusiness suite. The current backup and recovery processes for this service are deemed sufficient and are tried and tested. This along with the expected replacement of the system in under 3 years influenced the decision to close this project to reduce the overall compliance burden in 17/18.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
August 2017 | BLUE | 85.0 days | 88.0 days | 0.0 |