Project Brief
Document Sign-off
Name | Role | Date signed off |
---|---|---|
Terry Fox | Project Sponsor | 10-Nov-16 |
Anne Mathison | Project Manager | 10-Nov-16 |
Pam Baillie | Payroll Business Lead | 10-Nov-16 |
Susan McLaren | HR Business | 9-Nov-16 |
Nikki Stuart | Programme Manager | 10-Nov-16 |
Anne Finnan/ John Chan / Ron McLeod | CSG Applications Support Manager | 10-Nov-16 |
Mike McMonagle/Stella MacKinnon | CSG Development Manager | 9-Nov-16 |
Mark Lang /Emilio Perez-Lopez/ Gordon McKenna | Developement Technology Manager | 10-Nov-16 |
Heather Larnach | Technology Management Manager | 1-Nov-16 |
Apply annual HM Revenue and Customs (HMRC) legislative patches along with any security patches released by Oracle. This project will also cover any additional patches required to meet the universities legislative compliance
This is an annual compliance projects that must be progressed each year to ensure the University meets its statutory HMRC requirements. The Project includes;
- Data refresh (clone) of the database and application
- Outstanding pre-requisite patches needed for the Tax Year End patches
- Outstanding mandatory security patches
- All Mandatory Tax Year End patches and any agreed optional patches
- Any updates for the University to meet its P60 obligations.
It may be prudent to point out that potential changes relating to the Scottish Rate of Income Tax and other devolved powers may result in payroll changes which have not traditionally formed part of the annual maintenance programme, but would be expected to be covered in this initiative.
Additional compliance work may be required to be included in these annual projects. A decision will be made in the previous year’s planning as to whether the expected changes require a separate project or if the annual maintenance project can subsume this effort. The following HMRC compliance changes are expected for 16/17;
- Salary sacrifice (16/17) – minor change anticipated, to be included in Annual Maintenance project.
- Apprenticeship Levy (16/17) - minor change anticipated, to be included in Annual Maintenance project
Version Control
Version | Date | Author | Details |
0.1 | 1-Nov-16 | Anne Mathison |
Brief updated after 11 -Oct review meeting |
0.2 | 2-Nov | Anne Mathison | Brief updated after 2-Nov meeting |
0.3 | 10-Nov | Anne Mathison | Small updates after Brief reviewed |